A Study of Identifying Significant Variables of Delays in Road Construction Via Structural Equation Modelling (SEM)

  • Authors

    • Aboubaker. Y. Y Alfakhri
    • Amiruddin Ismail
    • Muhamad Azry Khoiry
    • Shaban Ismael Albrka
    • Abdurauf B. Z Alshetwi
    • Mohammed Saleh Alghadi
    2018-05-22
    https://doi.org/10.14419/ijet.v7i2.29.14278
  • road projects, delay variables, Structural Equation Model [SEM], Confirmatory Factor Analysis [CFA], Libya
  • Delays have always been a major concern in road construction projects throughout the world, with significant financial and social impacts for stakeholders, and the occurrence of schedule delays has a serious impact on project investment, efficiency, cost, and reputation. Libya is one of the countries faces all these delay issues. This study explored variables of delays in road construction via Structural Equation modelling SEM.  Drawing upon an earlier studies, combined with interviews of road experts. Confirmatory factor analysis CFA was applied to extract significant variables based on the questionnaire results to verify the relationships between the significant variables [8 Factors and 3 Effects] identified in road construction. Eleven variables were found to have significant impacts on delays in road construction. The results of the goodness of fit [GOF] showed that chi square is significant at 0.000 levels. Overall, Based on the CFI, TLI, and IFI indices with values more than the cut off value of 0.9 the model had good fit of data. Further. The root-mean-square error of approximation [RMSEA] was 0.033 which was within the perfect fit range. Additionally. The Relative CMIN/df [1.276] was less than 5 showed the good fit of the model and it was found that the unstandardized regression weights were all significant by the critical ratio test [> ±1.96, P < 0.001]. So the study has shown that CFA can quantify comprehensive relationships among a broad range of variables and contribute to resolving problems commonly experienced in the road construction industry.

     

  • References

    1. style='font-size:8.0pt;mso-fareast-font-family:Calibri'>
    2. field-begin'> ADDIN EN.REFLIST
    3. style='mso-element:field-separator'>[1] Abounahia A. Construction Delays Causes and Consequences. Unpublished MSc thesis, Department of Engineering Management El-Fateh University, Tripoli, Libya. 1998.

      [2] Mok KY, Shen GQ, Yang J. Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management. 2015;33[2]:446-57.

      [3] Pinto A, Nunes IL, Ribeiro RA. Occupational risk assessment in construction industry–Overview and reflection. Safety science. 2011;49[5]:616-24.

      [4] Hamzah N, Khoiry M, Arshad I, Tawil NM, Ani AC. Cause of construction delay-Theoretical framework. Procedia Engineering. 2011;20:490-5.

      [5] Abbasi MS, Tarhini A, Hassouna M, Shah F. SOCIAL, ORGANIZATIONAL, DEMOGRAPHY AND INDIVIDUALS'TECHNOLOGY ACCEPTANCE BEHAVIOUR: A CONCEPTUAL MODEL. European Scientific Journal. 2015;11[9].

      [6] Orozco J, Tarhini A, Tarhini T. A framework of IS/business alignment management practices to improve the design of IT Governance architectures. International Journal of Business and Management. 2015;10[4]:1.

      [7] Tarhini A, Ammar H, Tarhini T. Analysis of the critical success factors for enterprise resource planning implementation from stakeholders’ perspective: A systematic review. International Business Research. 2015;8[4]:25.

      [8] Tayeh M, Al-Jarrah IM, Tarhini A. Accounting vs. market-based measures of firm performance related to information technology investments. 2015.

      [9] Doloi H, Sawhney A, Iyer K, Rentala S. Analysing factors affecting delays in Indian construction projects. International Journal of Project Management. 2012;30[4]:479-89.

      [10] Meng X. The effect of relationship management on project performance in construction. International journal of project management. 2012;30[2]:188-98.

      [11] Ochieng EG, Price A. Managing cross-cultural communication in multicultural construction project teams: The case of Kenya and UK. International Journal of Project Management. 2010;28[5]:449-60.

      [12] Kazaz A, Ulubeyli S, Tuncbilekli NA. Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management. 2012;18[3]:426-35.

      [13] Marzouk MM, El-Rasas TI. Analyzing delay causes in Egyptian construction projects. Journal of advanced research. 2014;5[1]:49-55.

      [14] Semple C, Hartman FT, Jergeas G. Construction claims and disputes: causes and cost/time overruns. Journal of construction engineering and management. 1994;120[4]:785-95.

      [15] Yates J, Epstein A. Avoiding and minimizing construction delay claim disputes in relational contracting. Journal of Professional Issues in Engineering Education and Practice. 2006;132[2]:168-79.

      [16] Ghaffari A, editor Developing a Model for Risk and Responsibility Management Share Amongst Stakeholders Consortium in Construction Projects. Advanced Materials Research; 2013: Trans Tech Publ.

      [17] Khalid Khair1 HF, Zainai Mohamed3, R. Mohammad. Causes and Effects of Delay Factors in Road Construction Projects in Sudan. International Journal of Applied Engineering Research. 2016;11:9526-33.

      [18] Abd El-Razek M, Bassioni H, Mobarak A. Causes of delay in building construction projects in Egypt. Journal of construction engineering and management. 2008;134[11]:831-41.

      [19] Chan DW, Kumaraswamy MM. A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of project management. 1997;15[1]:55-63.

      [20] Lo TY, Fung IW, Tung KC. Construction delays in Hong Kong civil engineering projects. Journal of construction engineering and management. 2006;132[6]:636-49.

      [21] Sambasivan M, Soon YW. Causes and effects of delays in Malaysian construction industry. International Journal of project management. 2007;25[5]:517-26.

      [22] Sweis G, Sweis R, Hammad AA, Shboul A. Delays in construction projects: The case of Jordan. International Journal of Project Management. 2008;26[6]:665-74.

      [23] Assaf SA, Al-Hejji S. Causes of delay in large construction projects. International journal of project management. 2006;24[4]:349-57.

      [24] Haseeb M, Bibi A, Rabbani W. Problems of projects and effects of delays in the construction industry of Pakistan. Australian journal of business and management research. 2011;1[6]:41.

      [25] Toor SUR, Ogunlana SO. Problems causing delays in major construction projects in Thailand. Construction Management and Economics. 2008;26[4]:395-408.

      [26] Al-Hazim N. Delay and cost overrun in road construction projects in Jordan. International Journal of Engineering & Technology. 2015;4[2]:288-93.

      [27] Aziz RF, Abdel-Hakam AA. Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal. 2016;55[2]:1515-39.

      [28] El-Sayegh SM, Mansour MH. Risk assessment and allocation in highway construction projects in the UAE. Journal of Management in Engineering. 2015;31[6]:04015004.

      [29] Khalid Khair, Hazir Farouk, Mohamed Z, Mohammad R. Causes and Effects of Delay Factors in Road Construction Projects in Sudan. International Journal of Applied Engineering Research. 2016;Volume 11[Number 18 [2016] pp]:9526-33.

      [30] Mahamid I, Bruland A, Dmaidi N. Causes of delay in road construction projects. Journal of Management in Engineering. 2011;28[3]:300-10.

      [31] Callahan MT. Construction delay claims: Aspen publishers; 2010.

      [32] Abdul-Rahman H, Wang C, Takim R, Wong S. Project schedule influenced by financial issues: Evidence in construction industry. Scientific Research and Essays. 2011;6[1]:205-12.

      [33] Kaliba C, Muya M, Mumba K. Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management. 2009;27[5]:522-31.

      [34] Hasan R, Suliman SM, Malki Y. An investigation into the delays in road projects in Bahrain. International Journal of Research in Engineering and Science. 2014;2[2]:38-47.

      [35] Honrao MY, Desai D. Study of Delay in Execution of Infrastructure Projects–Highway Construction. International Journal of Scientific and Research Publications. 2015.

      [36] Shebob A, Dawood N, Xu Q, Egbu C, Lou E. Analysing construction delay factors: A case study of building construction project in Libya. Management. 2011;1005:1012.

      [37] Wei KS. Causes, effects and methods of minimizing delays in construction projects. A project report. 2010.

      [38] DeVellis RF. Scale development: Theory and applications: Sage publications; 2016.

      [39] Hair J, Anderson R, Tatham R, Black W. Multivariate data analysis with readings [4th Eds.]. NJ: Prentice2Hall, Inc. 1995.

      [40] Bentler PM. Multivariate analysis with latent variables: Causal modeling. Annual review of psychology. 1980;31[1]:419-56.

    4. mso-fareast-font-family:Calibri;mso-ansi-language:EN-US;mso-fareast-language:
    5. KO;mso-bidi-language:AR-SA'>
  • Downloads

  • How to Cite

    Y. Y Alfakhri, A., Ismail, A., Azry Khoiry, M., Ismael Albrka, S., B. Z Alshetwi, A., & Saleh Alghadi, M. (2018). A Study of Identifying Significant Variables of Delays in Road Construction Via Structural Equation Modelling (SEM). International Journal of Engineering & Technology, 7(2.29), 893-898. https://doi.org/10.14419/ijet.v7i2.29.14278